Salzbach viaduct. Dismantling a bridge in Germany using a directed explosion

Reisch Sprengtechnik GmbH carried out the demolition work for the 304-meter sections of the bridge.
Approximately 10,000 square meters of reinforced concrete were processed.
1150 wells were drilled, 100 heavy anti-explosion mats were installed.
The project involved 6 employees who carried out all the training.
70,000 m³ of bridge structures were collapsed and about 198 kg of explosives were placed, causing the bridge to collapse.
The bridge was blown up on November 6, at 12 noon.